Question 1:

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine HoursDue Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

  • Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5)
  • What is the makespan?
  • How much machine idle time is there?
  • How much idle time (waiting time) is there for each job?
  • When is each job delivered?
  • Which department is the bottleneck?
  • Calculate the machine utilization?

Question 2:

A public accounting firm requires the following activities

for an audit:

Activity

Immediate Predecessor

Activity time

A

3

B

A

2

C

5

D

B, C

2

E

A

4

F

B, C

6

G

E, D

5

  • Draw a network for this project?
  • Make a forward pass and a backward pass to determine ES, LS, EF, and LF?
  • What are the critical path?

** A clearer version of the table with attachments

Get 15% discount on your first order with us
Use the following coupon
FIRST15

Order Now

Hi there! Click one of our representatives below and we will get back to you as soon as possible.

Chat with us on WhatsApp